Our contractor completed the last official piece of work on the building early this week by pouring a new access ramp for the front sidewalk.


We also had a sign company install our sign- which had been permitted separately.  Here are some shots of the process:



Now we're only lacking one test of our new fire hydrant and two inspections before we can use our new space.  As it is highly unlikely that all of this will happen in time for this Sunday (3/22), we'll be meeting one last week (hopefully) at Delightful Inspirations.  

So far we've hit a couple of small snags as different inspectors are asking us to do opposite things.  Please pray that the rest of this process will go smoothly and quickly and that we'll be able to start using the building as soon as possible.